*- Scope of work:

Excavating and filling specified parts which were carried out in dry conditions to achieve formation level as per specifications and drawings. It also includes all necessary cofferdams, temporary ramps, temporary dewatering with pumps and reclamation the surrounding area.

o

  • Client: Al Zorah Development LLC

  • Consultant: COWI

  • Main Contractor: China Harbor Engineering

  • Duration: 5 months (2011)